Overview of the most important references from the last 3 years
Project Timeline
2014
VLB Leitungsbau GmbH
2014
Construction of a 53 km, 400 kV high-voltage line – tower assembly and support during stringing operations, SvK Sweden, 1,636 tons.
2018
CTEAM Leitungsbau Österreich GmbH
2018–2020
Pre-assembly, assembly and refurbishment of 220 kV towers, St. Peter – Ernsthofen, 2,400 tons.
2019
CEIT S.p.A.
2019–2020
Open Fiber – Apulia, excavation works for fiber-optic installation.
2019
CTEAM Leitungsbau Österreich GmbH
2019–2021
Pre-assembly, assembly and refurbishment of 220 kV towers, Weinviertel line, 615 tons.
2020
TERNA S.p.A.
2020
Safety intervention on section P.1–3, 132 kV line No. 847 “Albiano – Avenza”. Replacement of two towers and stringing works.
2020
LTB Leitungsbau GmbH
2020
Pre-assembly and refurbishment of 380 kV towers, Kupferzell – Stalldorf.
2020
CTEAM Leitungsbau Österreich GmbH
2020–2021
Pre-assembly, assembly and refurbishment of 110 kV towers, UW Groß Gerungs – UW Gmünd, 1,479 tons.
2020
COGET Impianti S.p.A.
2020–2021
Pre-assembly and refurbishment on the 380 kV line, Weinviertel line – Auersthal.
2021
TERNA S.p.A.
2021
Diversion of 132 kV lines T.141–T.142 near the Chiari (BS) substation. Dismantling and assembly of two towers and stringing operations.
2021
TERNA S.p.A.
2021
Refurbishment of foundations and tower structures of 220 kV line No. 22121B1 “Villasor 1 – Selargius”, AOT Cagliari 150 kV.
2021
European Trans Energy GmbH
2020–2021
Pre-assembly, assembly and refurbishment of the 110 kV line Ebensfeld – Steinbach, 324 tons.
2022
CTEAM Leitungsbau Österreich GmbH
2021–2022
Pre-assembly, assembly and refurbishment of 110 kV towers, Ried – Raab, 565 tons.
2022
VLB Leitungsbau GmbH
2021–2022
Pre-assembly, stringing operations and refurbishment of 380 kV line Salzburgleitung, Sections II + III (AT), 1,900 tons.
2022
VLB Leitungsbau GmbH
2022–2023
Pre-assembly and refurbishment of 110 kV line Pottenbrunn – Bergern.
2022
LTB Leitungsbau GmbH
2022
Pre-assembly of 380 kV overhead line Bertikow – Pasewalk, 460 tons.
2022
LTB Leitungsbau GmbH
2022
Refurbishment of 110 kV towers, UA Hiesfeld, BL 0816 (25 tons shafts, 4.5 tons crossarms).
2022
LTB Leitungsbau GmbH
2022–2023
Pre-assembly of 380 kV line Uckermarkleitung – Lot 6.1 new construction, 1,550 tons.
2023
50Hertz
2023–2024
Pre-assembly, assembly and dismantling of 380 kV line Röhrsdorf – Weida – Remptendorf, Lot 3, 1,485 tons.
2023
CTEAM Leitungsbau Österreich GmbH
2023–2024
Pre-assembly and assembly of 220 kV line Ernsthofen – Hütte Süd (AT), 2,200 tons.
2024
LTB Leitungsbau GmbH
2024–2026
Pre-assembly, assembly and dismantling of 380 kV line Ultranet, Section B1, Pkt. Wallstadt – Converter Phillippsburg, Lots 1–2–4–6, 5,000 tons.